Hi,
Made some progress on the pack build, in fact the pack is done

at last
Found some electrical rail (don't know the real name for that) in the trash, cut it to 4.5 cm (1.77')
pieces and it slides on like a glove, no more exposed terminals
Reinforced with some more tape
I know what you thinking: why didn't you cover the main terminals with the same rail ?
A: I have 10.5 cm (4.1') high clarens for this pack, so if I cover the mains it will exceed that.
Also I had to raise the pack of the ground so it will not rest on the main terminal.
Did a short road test with my 1Kw stand up scooter (brushed motor), I'm hooked, this power is crazy. R.I.P SLA's
I used turnigy watt meter, got 3Kw picks and about 1.1Kw continuous. Although the motor wires and controller go hot,
the main pack terminals wasn't even slightly warm, I guess it means I did a good job ?
The pack after the test
Michael